Storage Facility Site Work

 

RPH recently assisted with the phasing plan of a new 3-story retaining wall at a proposed storage facility addition with one of our long term clients. The scope of work required an extension of an existing underground passageway to provide access into the addition.  The retaining wall is to be constructed in 3 separate phases with large-scale excavation, temporary concrete shoring walls, and construction of the basement footings/foundation walls.  The phasing diagrams were needed to assist with approval for the retaining wall permit, and to provide clear direction to the General Contractor. We enjoy exploring new ways to communicate design ideas outside of typical 2D drawings- and working to make the construction process go as smoothly as possible.